THE go-ahead is set to be given to the second phase of a £3.6m improvement scheme to combat traffic congestion in London Road, Headington.
Oxfordshire County Council wants to spend £2.3m to install a bus gate on the arterial route to reduce delays to Oxford-bound bus passengers and spruce up the Headington shopping precinct.
However, road users will face up to nine months of delays if the scheme is approved by the county’s transport chief Ian Hudspeth on Thursday next week. >
Councillors and civic leaders have demanded the authority learns lessons from the £1.3m first phase of the scheme which over-ran by two months and caused misery for more than 14,000 motorists who use the road every day.
Headington city councillor David Rundle said: “Everyone acknowledges the first phase did not go well.
“The county need to take a deep breath and make sure they are confident this will not be as bad a mess as the first stage.
“Stage one was unnecessarily disruptive and this phase is bound to be worse because of the significance of the district centre of Headington.
“It is absolutely crucial that does not going to happen again.”
Council officers have recommended the second phase of works for approval and if the plans are rubberstamped next week, roadworks between Osler Road and Wharton Road will begin in spring 2010.
The first phase which saw a new outbound bus lane between Gipsy Lane and Osler Road and a 20mph zone between Pullens Lane and Headley Way took ten months and finished at the end of May.
The plans will also see a well-used subway in the area controversially filled in and replaced by an above ground pedestrian crossing.
Croft Road resident and community campaigner Mick Haines, 68, gathered 2,511 signatures on a petition in March to stop the closure of the subway.
However, the county council said 58 per cent of Headington residents were in favour of the plans when they realised there would be a replacement crossing.
James Bloice Smith, of the group Headington Action charity which aims to improve the area, said: “We have been very impressed with the level of consultation.
“It’s been hugely better than anything we have experienced before locally.
“However, we hope the management and staging of this project is hugely better.
“The previous disruption was a nightmare and a lot of people found getting through Headington so slow they found other routes to get into the city.”
Councillor Ian Hudspeth said: “We are of course very keen that an overrun of the nature experienced on the recent London Road roadworks should be avoided.
“Those lessons will be firmly applied.”
Transport planning officer Joy White said: “This scheme would contribute significantly towards tackling congestion by reducing delay to the large number of bus passengers that use the route and encouraging greater bus use, as well as reducing delays to general traffic caused by congestion at bus stops.”
She added: “It would improve road safety through a reduced speed limit and a new design to reinforce it and improve the street environment.”
Headington shops are bracing themselves for the works with hairdresser Matthew Clulee claiming he suffered a 35 per cent drop in sales at this London Road outlet during the first phase of roadworks.
He said: “It’s unbelievable. The roadworks have been far and away the worst problem for our shop.
“We had what was a really thriving business here but now lots of our Headington customers go to our shop in Oxford because they say it’s easier to get to.”
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel