County councillor and education expert John Howson criticises the Government for delays in delivering Oxford's new Swan School
WHAT a mess the process of creating a new secondary school for pupil in Oxford has become.
Way back when government know what it was doing and how to conduct itself properly, the creation of new schools for an expanding population was a partnership between the relevant local authority and the government department in London.
Then came Labour’s academy programme and then Michael Gove’s desire to promote so-called ‘free schools’.
Especially in respect of the latter, local authorities became side-lined once they had identified a need or even if they had not done so, if a promoter want to create a ’free school’ in a particular area. The same was also true for UTCs (university technical colleges) and studio schools.
Oxfordshire’s identification of the need for new secondary school in Oxford in their Pupil Place Plan in 2015 attracted the interest of Toby Young, the promoter of a free school in West London.
As a result, a second proposal for a free school was launched by what is now the River Learning Trust – a multi-academy trust based in Oxfordshire.
This trust was successful in being granted permission to operate the new ‘free school’ in September 2015.
Local authorities can oversee the development of new academies and Oxfordshire has successfully done so for several new schools, including the new secondary school in Didcot, which opened on time.
However, the development of free schools is the responsibility of the Education and Skills Funding Agency.
In July 2016, I asked a question at the county council about the possible site for the new school and was told: “The sponsor’s and EFA’s current preferred location for The Swan School remains The Harlow Centre.”
The cabinet member who answered did not know when the school might open and how it would be linked to the annual school admissions.
Fast-forward two years until 2018, and at county council in March 2018 I was told in answer to another question that ‘the completion for the Swan School may not be ready until 2021’ and a planning application should be submitted by the end of May.
I was told that in summer 2019 Meadowbrook College, on the proposed Swan School site, should start to be demolished and its new build would complete by September 2020.
In early 2021 the Swan School should be complete but until then the school will probably be in temporary accommodation for two years, the answer added.
So, by March 2018, it was already known that the school would be two years late and have to open in temporary accommodation.
At county council in July, I asked more questions about progress, including if we had absolute assurance that the Education and Skills Funding Agency would not pull the Swan School given the delay in receiving planning permission.
The cabinet member undertook to ask the agency for an answer.
We can assume that the trust still wish to go ahead with the scheme, as there is still a need for a new school. With the appointment of a headteacher, this must still be the intention.
However, it seems increasingly unlikely that it will open in 2021, and temporary accommodation will need to be found if the first round of pupil is to arrive in 2019.
It is assumed that planning permission will be required for any temporary buildings needed from September 2019.
In July 2018, I asked at county council whether, in view of the very large number of children from within the EU that are within city primary schools, who would be transferring into the secondary sector in the next few years’, the school might not be built as a result of Brexit.
I have not received an answer to that question.
The city council’s East Area Planning Committee turned down the planning application for the school at their meeting in September - a decision that was called in and will be reconsidered today.
The county council’s cabinet will discuss the Swan School in an exempt session tomorrow.
The whole saga from start to the current uncertain situation shows the lack of coherence in our present education system.
Under the former rules, it seems certain that the county council, having identified the need for a secondary school, would have designed and built it in time for a 2019 opening, possibly even 2018.
Even had the school been designated an academy, this might have been achieved.
The creation of the school as a ‘free school’ has created delay and allowed concerns about the site to create the present high degree of uncertainty.
The situation for parents in the city of Oxford is now complicated with respect to admissions to secondary school for 2019.
Parents in Oxfordshire have been short-changed by this shambolic process and county council taxpayers stand to lose out for up to three years if the temporary accommodation requires pupils to be offered free transport to school.
Should the new school not be built, the ongoing cost to council taxpayers in additional transport costs could be considerable, depending upon how many of the 1,260 pupils would be eligible for free transport.
In the present financial climate, this cost could probably only be met by cutting other council services.
Were Oxford part of a unitary council structure, then school place planning would have been a function of the council deciding the planning application.
Under the two-tier system currently in operation across Oxfordshire, the city council is the planning authority, but the county council has the responsibility for pupil place planning and the number of schools.
However, the county has lost control over the building of these new schools.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel